Sunday, 7 December 2014

Week 8 (1-5 Dec 14) - Underslab Insulation, formwork

Installation of the XPS foam began on the weekend in very hot (for Melbourne) conditions.  The detailing of how the XPS foam was to be installed was not well defined and practically became extremely difficult to come up with a workable solution.

What should have been installed

The initial concept for the build was to put the foam on top of a structural slab with a further screed slab on top.  This would have allowed for a very simple installation of the insulation with minimal thermal bridges.  Unfortunately, the structural engineer persuaded us to use a single slab on a cost basis.  In reality, the original concept would have been less expensive and much simpler to implement.  Lesson learnt!

What was installed



The issues were as follows ;
The foam was not self supporting and needed to be pegged in position.  As the raised elements of the  slab i.e. the bits between the beams was not precisely cut, because in a normal slab the concrete fills the voids the foam had to be backfilled to prevent the foam being pushed in when the concrete was being poured.  This caused another problem as before the concrete is poured there is nothing to support the backfill.  Various attempts at finding a solution were tried and failed. Finally, it was decided to leave pegs in place under the waterproof membrane that keep the foam in place.   unfortunately this adds a thermal bridge through the foam in the bottom of the trench and creates a void between the concrete and the XPS.

And yes, the XPS was suitable to be placed below the damp course layer.  According to the manufacturer's specification a typical reduction in insulation of performance of 0.6%(by volume) can be expected due to water  ingress.  (see - http://www.knaufinsulation.com.au/media/1000777/climafoam_xps_board_datasheet_web.pdf)

The sequence of events for the foam installation are as follows;

1/ Foam is cut and placed around the sides of the beams - in this case either side of a construction joint.  The tops of the piers are exposed.

2/ XPS is added to the area between the piers and sand is backfilled behind the foam to stop the concrete from collapsing the foam inwards.

 3/ Top sheets are laid out and pier locations are marked so they can be cut to expose the piers

 4/ We started cutting the piers holes in the XPS with a hot knife but found a simple jig saw with a long blade was faster and provided a better finish.


5/ The damp proof plastic is then laid over the XPS and cut to expose the piers

 6/ The piers holes are then sealed to provide a continuous damp proof layer

7/ Around the outside edge of the slab the first layer of ICF foam is nailed to the inside of the form work.  This becomes the start of the ICF walling system and provides the insulation for the slab edge.
The ICF supplier is Ecoblock (http://www.eco-blockaustralia.com.au/) - sold via Polycon (http://www.polycon.com.au/) in Victoria. 


8/ Where dowels are required in the edge beam piers a pultruded fibreglass dowel is used to reduce thermal bridges between the ground and edge beams. These dowels are 20mm and manufactured by V-Rod and supplied by Inconmat (http://www.inconmat.com.au/) in SA.

9/ The ICF corner profile is thicker than side wall

Other ICF suppliers worth consideration;



Week 6/7 (17-28 Nov 14) Gabion Wall, Footings

The main services trench to front gate completed.  The electricians were on site to add the mains cables and data for intercom and other services.  In the same trench there was also gas, water, storm water for driveway drain and additional water pressure pipe to allow tank water to be pumped to front fence gardens.

On the weekend we put in another retaining wall towards the back of the block to provide stability to the path and slope.   This time we used a gabion cage wall or wire baskets filled with rocks.  The time consuming part was the construction of the cage but we were able to move 8.3tons of rock with the assistance of the Vemeer mini loader and completed the wall in one day.


The end result was in fitting with the surrounding bush area.


The concretors were back on site to complete front fence footings and get slab set up for formwork and slab pour.




Yet another digger - I have officially lost count now..


The XPS foam arrived on site, 5 piles, 150 sheets, 400m2.


Week 5 (10 Nov 14) - Site Clean Up and Plumbing Preparation

Site cleanup - moved the 50+ m3 of dirt removed from pier holes to a location easily loaded to be taken away - another machine but since I was driving it there were no photos..  Yet another machine and truck to remove the dirt..











And almost as soon as the last truck left the plumber arrived on site, measured up and began making more dirt!




Greywater
We thought it would be a good idea to add a grey water diverter system to the build so that we could reuse the water on the garden.  Perhaps its the shiny new desal plant that Victoria installed a couple of years ago, or the lack of clarity from local councils about regulations and requirements but nobody seems to buy these systems any more.  The system we were looking for would divert water immediately to the garden and not store any water for more than 24hours (regulation!).  Also, it was important that any filters would be easy to clean, and hopefully not needing cleaning on a regular basis.  The Greyflow PS (http://www.greyflow.net.au/index.php/product-selection-guide/grey-flow-ps) was chosen.  It had the advantage of being staged installed - i.e. the basic system could be installed with the plumbing and the pump and control system could be added later, once the house is complete.  It also, has the option of adding an automatic cleaning system that means filters only need to be cleaned annually.




Piers
Of the 155 piers we got 4 wrong...
We just realised that the 4 of the piers we bored and filled with concrete were in the wrong place.  Of course these were under one of the two construction joints!! However, luckily they were some of the piers that we also bored to 600mm rather than 450mm so they are still under the joint..